Please see below details of scheduled works on the Physics refurbishment and Isolab projects for next week.
Should you have any queries regarding these projects please contact the Senior Project Manager, Helen Wood, via the Facilities Helpdesk on facilities.helpdesk@lancaster.ac.uk or 01524 593333.
Dear all
Please see below details of scheduled works on the Physics refurbishment and Isolab projects for next week.
Physics additional note:
All staff must NOT use the central staircase unless as a means of escape in an emergency. This is part of the contractor’s site and for health and safety reasons staff and students must not use this area apart from in the event of a fire or other emergency.
Physics scheduled works
Section 2 A
- M&E installation
- Window installation
- Door and frame replacements
Section 2
- Asbestos surveys
- M&E surveys
- External groundworks to new toilet block
- Siting of new gate house and hoarding completion
- Soft strip demolition
Isolab scheduled works
- Electrical 2nd fix
- Mechanical 2nd fix
- E.M Shielding fixing pattress brackets & door reveals
- Main door installs & final testing to glazing
- Pod doors head track install
- Ground workers installing ducting/external area prep and service trench works
- No noisy or disruptive works to Isolab internally, but ground workers will be using a stihl saw on the service trench works
Should you have any queries regarding these projects please contact the Senior Project Manager, Helen Wood, via the Facilities Helpdesk on facilities.helpdesk@lancaster.ac.uk or 01524 593333.
Madeline Asquith
Closure of phase II Physics
The contractors now have control of the second phase of the Physics building. We can only enter this area in the course of an emergency evacuation. Please do not use the stairs at the interface between phases. Our use of this area will delay the works.
Shonah Ion
Fire alarm testing next week
As usual, the fire alarm system and the evacuation processes for the Physics building will be tested at some time next week. Our muster point is unchanged at the pavement between the Isolab and the perimeter road. On hearing the alarm make safe what you are doing if necessary and make your way to the nearest safe exit and gather at the muster point. The main front door is the main exit route for most users of the building. The exit at the bottom of the interface stairs can be used and the route would then be along the Physics building towards Alexandra square and then to the right and come on to the spine. From the spine you need to make your way to the muster point via a safe route. The Faraday building would be the most convenient generally. Please make yourself familiar with the escape routes from any building you work in.
Obviously as the spine works develop the escape routes may be subject to change.
Shonah Ion
Safety Inductions resume
The monthly safety inductions will resume on normally the first working Thursday of the month. The next one is a running item on this bulletin.
October Safety Induction 3pm in Bowland North SR3 on 13th October.
Shonah Ion